Heritage Restoration, Inc.

Week Ending in 7/28

Work began Wednesday 7/26, during this week, scaffolding was brought to the Meeting House and setup. Half of the building was also cleared of clapboards. These hand planed clapboards (claps) were installed during the 1820’s with hand wrought nails. Claps and nails that are still in fair to good conditions are being save to be used in spot repairs on other elevations of the building that only need repair rather than replacement.

It would be helpful to have volunteers to assist in remove nails from the clapboards. Please e-mail Alex at alex@heritagerestoration.net with any questions!

Work begins!