Heritage Restoration, Inc.

Week Ending in 8/31

All timber frame repairs are complete! Fiber glass rods have been inserted into two place as a safeguard for future stability.

The corner and mud boards have also been fabricated and are being attached to the home. Tar papering the primary elevation of the meeting house is also nearly complete. Clapboards a planned to go up on the home next week!